Borehole investigation is done by the service provider who is an expert on it. After finalizing the borehole layout, an investigation of the condition of the ground is done. As discussed in the article "How to select number of boreholes", the number of boreholes are drilled to get the recommendation for foundations.

Commonly, the standard penetration method (SPT) is used to find the condition of the ground. It is a method that provides the stiffness of the soil based on the penetration when a constant pressure applied.

Based on the SPT values and observations made on the samples taken during the coring, allowable bearing capacity for foundations is provided after doing necessary calculation by taking into account the types of soil layers present and the overburden where the foundations are rested.



For deep foundations, drilling the ground up to the fresh rock and coring in the fresh rock are done to check the soil and rock profiles. The depth of the coring in the rock depends on the condition of the rock. If the rock is weak, the depth of the coloring could be increase to examine the condition of the groud.

There are several parameters required for designing a deep foundation.
  1. Skin friction of the soil above the weathered rock
  2. Skin friction of Weathered rock
  3. Negative skin friction of soil if any
  4. Skin friction of the rock
  5. End bearing of rock 
The above values will be provided in the geotechnical investigation report with a necessary recommendation for the foundation that includes the depth of socketing. The friction of the soil can be calculated based on the soil parameters or based on the SPT values. There are many methods to evaluate the skin friction of the soil.

End bearing of the rock is decided commonly based on the uniaxial compressive strength o the rock which is evaluated from the test done form the rock samples taken during the coring.

Usually, measurements are taken at ta depth of 1m intervals. SPT values are tested and recorded at each 1m depth of drilling. The following figure indicates the sample borehole log.



The time in which the hammer bouncing is considered as the SPT is grader than 50. When there are very stiff layers this can be observed. The borehole log will be indicated as shown above figure at a depth around 6m when the hammer is bouncing.

The article published in Wikipedia "Standard Penetration Test" states the ranges of SPT values based on the relative density of soil. The same article could be referred for further reading on standard penetration test.

The following video could be referred for the method of soil investigation.





Comments

Popular posts from this blog

How to Select Number of Boreholes

Borehole layout is decided based on the area to be covered and the type of the foundation be constructed. In addition, the importance of the structure is also considered in selecting the number of boreholes to be done. For example, when a high rise building is designed, knowing the conditions of the ground preciously is very very important to the designer. Thus, the planning of the borehole layouts is done. Small Projects In low rise buildings, we may plan the number boreholes based on the condition of the ground and cover the whole footprint of the building. For small buildings such as two 2-4 story, constructed in a weak ground, one might select one borehole considering the spread of the structure. Large Projects Buildings such as high rise buildings, it is required to plan the borehole layout properly and accurately to cover the area covered by the structure. The number of boreholes is depended on the area of the structure and based on the condition of the ground pr...

Testing before Construction

Testing in construction is done in different stages. Preconstruction, during construction and post-construction tests, is done to control the quality and to assure the quality of the construction work. For example, preconstruction tests can be identified as the testing of materials, testing of ground conditions for foundation, etc. Testing of the during construction is a must to assure the quality of construction work. For example, testing of concrete cubs is done to check whether the concrete has achieved the strength. Further, there is a post-construction check such as a test on completion. For example, check the lift after installation for its loads capacity is done as post cost construction testing. Testing in construction is discussed under three main categories in this article. Firstly, it is required to test the condition of the ground for evaluating the types of foundation based on the geotechnical condition of the ground. Secondly, post-construction testing and testing...

Testing in construction

Learn  Construction Material Testings  Techniques Sieve & Hydrometer Analysis Moisture Content Determination Atterbury Limit (LL, PL, PI, SL) Specific Gravity Bulk Desnsity/Unit weight Swell Index Test Proctor Compaction(Std, Mod) 4 days soaked CBR (Std, Mod) Permeability Test (Constant Head/Falling Head) PH Value, So4-- Content, Cl- Content of Soil/Ground Water Organic content of soil UU Tri Axial Compression Test Unconfined Compression Test Field CBR Test Consolidation Test Aggregate Crushing Value (ACV) 10% Fines Value of Aggregates Aggregate Impact Value (AIV) Los Angeles Abrasion Value (LAAV) Unconfined Compression Test of Rock Specific Gravity and Water Absorption of Aggregates Flakiness Index and Elongation Index Field Density Test Point Load Strength Index of Rocks Non Destructive Hammer Test on Concrete Compressive Strength Tests on Concrete Cubes/Paving Blocks/Hollow Blocks Compressive Strength Test of Clay Bricks